DHL North Apron Expansion

Cincinnati/Northern Kentucky Intl. Airport

  • 2016
  • Project Type: Concrete Paving

About this Project

This project consisted of over 210,000 SY of 18″ thick concrete paving, 230,000 SY of econocrete base, 80,000 tons of crushed aggregate base, and 20,000 LF of drainage pipe. This project had tight schedule requirements, and the concrete paving was completed in just over four months. 

    Contact Us

    6 + 6 =

    1648 Petersburg Rd. Hebron, KY 41048

    859-586-8890

    859-586-8891